Geer Park Elementary was constructed in 2005 and is situated on 4.85 acres. If the bond is approved, the building would be fully renovated. Estimated renovation cost: $17,802,212. For an overview, see the one page flyer regarding Geer Park.
Phase 1 (Years one to five)
- Secured vestibule/reception
- Shingle roofing replacement
- Technology and furniture upgrades
Phase 4 (Years 15 to 20)
- Major renovations to classrooms, media center, and gym
- Cafeteria and kitchen upgrades
- Site improvements including parking and playgrounds
- Major mechanical replacement
- Building enclosure such as windows and doors
- Major electrical replacement
- Major plumbing replacement
- Elevator replacement
Learn more about the 2026 transformational bond on the district website.